2016 Project Updates

2016 Project Updates

Shoulder Pulling:  Working on Range Road 221 A.  Have completed 1.5 miles, have been delayed by rain.

Shoulder Pulling Twp 472:  contractor is beginning this week (August 15th) Closed to local traffic only.

Pelican Point Paving:  Paving complete. 

Armena Paving:  Paving completed.

Project 3-12-15 (Twp Rd 422, from Range Road 225 to Highway 21) was awarded to Petrowest.  Construction started June 23rd.  Construction is complete.  Thank you for your patience during construction as the rain made it rather mucky!

Project 3-11-15 (Twp 434, from Highway 56 to Range Road 184) was awarded to Pidherney's and is scheduled to begin in August.  Construction is beginning at the east end.

     
 
Armena Paving   Pelican Point Paving